UPDATE: Inflector has acquired industry experts in fireproofing, firestopping application and HAZMAT waste removal, Donalco Inc., Ontario division. We are excited for the coming together of two incredible teams. Read more about the acquisition here.

EMERGENCY RESPONSE: 1 866 208-8736

Place Du Portage ceiling mid demolition
Place Du Portage interior ceiling gutted
Place Du Portage 1 - corner wall
Place Du Portage 2
Place Du Portage 3 - wall and ceiling
Place Du Portage 4 - wall and ceiling
Place Du Portage 5 - interior ceiling
Place Du Portage ceiling mid demolition
Place Du Portage interior ceiling gutted
Place Du Portage 1 - corner wall
Place Du Portage 2
Place Du Portage 3 - wall and ceiling
Place Du Portage 4 - wall and ceiling
Place Du Portage 5 - interior ceiling

Place Du Portage Asset Workplace Renewal – Interior Demolition

Project Type:

Commercial Asbestos & Lead Removal

Description:

Inflector was contracted under the FIA Group to execute asbestos abatement on Levels 2 through 10. Work began in early 2020 continuing until August of 2020 for the first 5 floors and through delays due to the pandemic. The second phase was delayed until April-May of 2021.

Work included Type 2 (moderate risk) asbestos removal of fire separations, exterior walls and bulkheads throughout. Contracted floors were vacant but the rest of the building was partially occupied and still in operation. Inflector set up separations to allow our work to proceed without affecting the rest of the building’s occupants. All work to date was on schedule and on budget. A crew of six people worked one floor at a time. Productivity was maximized by setting up the next floor while awaiting test results before tear down.

TTC underground

Toronto Transit Commission: North York Centre

The TTC North York Centre subway station contained fireproofing materials once used in construction that
Learn More
Caution sign warning of RotaVirus

Emergency Rotavirus Clean Up & Decontamination

Christy Lake Camp for kids contacted Inflector’s emergency response team directly, immediately after Public Health
Learn More
Government Conference Centre - Outside

Government Conference Centre

This project was completed within six months and required the removal of 3,500 tons of