UPDATE: Inflector has acquired industry experts in fireproofing, firestopping application and HAZMAT waste removal, Donalco Inc., Ontario division. We are excited for the coming together of two incredible teams. Read more about the acquisition here.

EMERGENCY RESPONSE: 1 866 208-8736

CHEO inside progress - insulation
CHEO inside progress
Insulation on a wall
Duct work
Worker setting up framing
Worker setting up framing
Worker taking asbestos material off a wall
Debris all over a floor
Worker collecting debris
CHEO inside progress - insulation
CHEO inside progress
Insulation on a wall
Duct work
Worker setting up framing
Worker setting up framing
Worker taking asbestos material off a wall
Debris all over a floor
Worker collecting debris

Children’s Hospital of Eastern Ontario (CHEO)

Project Type:

Mould Remediation, Commercial Asbestos & Lead Removal

Description:

When faced with the presence of mould and asbestos-containing materials across different locations and wings throughout the hospital, Inflector’s team discreetly mobilized to perform abatement and remediation procedures during the hospital’s operating hours. Any disturbances to staff and patients were mitigated, prioritizing the safety and well-being of all occupants within.

TTC underground

Toronto Transit Commission: North York Centre

The TTC North York Centre subway station contained fireproofing materials once used in construction that
Learn More
Caution sign warning of RotaVirus

Emergency Rotavirus Clean Up & Decontamination

Christy Lake Camp for kids contacted Inflector’s emergency response team directly, immediately after Public Health
Learn More
Government Conference Centre - Outside

Government Conference Centre

This project was completed within six months and required the removal of 3,500 tons of
Learn More